All formulas

Page 3 of 10 ยท 93 total
#FormulaExpressionLearn
21
Forward Pass โ€” Early Start (ES)
Schedule
ES = EF of predecessor + 1Learn more
22
Backward Pass โ€” Late Finish (LF)
Schedule
LF = LS of successor โˆ’ 1Learn more
23
Backward Pass โ€” Late Start (LS)
Schedule
LS = LF โˆ’ Duration + 1Learn more
24
Slack / Float
Schedule
Float = LS โˆ’ ES = LF โˆ’ EFLearn more
25
Critical Path Float
Schedule
Float = 0Learn more
26
Crashing
Schedule
Add resources to critical tasksLearn more
27
Fast Tracking
Schedule
Run sequential tasks in parallelLearn more
28
PERT / Beta Estimate
Estimation
E = (O + 4M + P) / 6Learn more
29
Triangular Estimate
Estimation
E = (O + M + P) / 3Learn more
30
PERT Standard Deviation
Estimation
SD = (P โˆ’ O) / 6Learn more

PMP, PMI, PMBOK, ATP, PgMP and PMI-ACP are trademarks of the Project Management Institute, Inc. PRINCE2 and ITIL are trademarks of AXELOS Limited. CSM is a trademark of Scrum Alliance, Inc. SAFe is a trademark of Scaled Agile, Inc. CBAP is a trademark of IIBA. All other trademarks are the property of their respective owners. MyPMP is an independent directory and is not affiliated with, authorized, endorsed by, or sponsored by any of these organizations.