All formulas

Page 1 of 10 ยท 93 total
#FormulaExpressionLearn
1
% Spent
Earned Value
PS = AC / BAC ร— 100Learn more
2
Planned Value (PV / BCWS)
Earned Value
PV = Planned % complete ร— BACLearn more
3
Earned Value (EV / BCWP)
Earned Value
EV = Actual % complete ร— BACLearn more
4
Actual Cost (AC / ACWP)
Earned Value
AC = Actual cost of work performedLearn more
5
Percentage Complete
Earned Value
PC = EV / BAC ร— 100Learn more
6
Cost Variance (CV)
Earned Value
CV = EV โˆ’ ACLearn more
7
Cost Variance % (CV%)
Earned Value
CV% = CV / EV ร— 100Learn more
8
Schedule Variance (SV)
Earned Value
SV = EV โˆ’ PVLearn more
9
Schedule Variance % (SV%)
Earned Value
SV% = SV / PV ร— 100Learn more
10
Cost Performance Index (CPI)
Earned Value
CPI = EV / ACLearn more

PMP, PMI, PMBOK, ATP, PgMP and PMI-ACP are trademarks of the Project Management Institute, Inc. PRINCE2 and ITIL are trademarks of AXELOS Limited. CSM is a trademark of Scrum Alliance, Inc. SAFe is a trademark of Scaled Agile, Inc. CBAP is a trademark of IIBA. All other trademarks are the property of their respective owners. MyPMP is an independent directory and is not affiliated with, authorized, endorsed by, or sponsored by any of these organizations.