All formulas
Page 2 of 10 ยท 93 total| # | Formula | Expression | Learn |
|---|---|---|---|
| 11 | Schedule Performance Index (SPI) Earned Value | SPI = EV / PV | Learn more |
| 12 | Estimate to Complete (ETC) Forecasting | ETC = EAC โ AC | Learn more |
| 13 | EAC โ if cost variance continues Forecasting | EAC = BAC / CPI | Learn more |
| 14 | EAC โ if schedule variance continues Forecasting | EAC = BAC / SPI | Learn more |
| 15 | EAC โ rebaseline (new ETC) Forecasting | EAC = AC + ETC | Learn more |
| 16 | EAC โ atypical variance Forecasting | EAC = AC + (BAC โ EV) | Learn more |
| 17 | EAC โ typical (CPI ร SPI) Forecasting | EAC = AC + [(BAC โ EV) / (CPI ร SPI)] | Learn more |
| 18 | To-Complete Performance Index (TCPI) Forecasting | TCPI = (BAC โ EV) / (EAC โ AC) | Learn more |
| 19 | Variance at Completion (VAC) Forecasting | VAC = BAC โ EAC | Learn more |
| 20 | Forward Pass โ Early Finish (EF) Schedule | EF = ES + Duration โ 1 | Learn more |
PMP, PMI, PMBOK, ATP, PgMP and PMI-ACP are trademarks of the Project Management Institute, Inc. PRINCE2 and ITIL are trademarks of AXELOS Limited. CSM is a trademark of Scrum Alliance, Inc. SAFe is a trademark of Scaled Agile, Inc. CBAP is a trademark of IIBA. All other trademarks are the property of their respective owners. MyPMP is an independent directory and is not affiliated with, authorized, endorsed by, or sponsored by any of these organizations.