MyPMPlearn live
← All templates
☁️
Free to try — your work auto-saves in this browser.
Saving to the cloud (sync across devices) is a paid feature. Unlock Change Request for $1/mo, or get everything with membership ($9/mo or $99/yr).
All apps + QMS · $9/mo or $99/yr
⚠️ Risk & Change
Risk & Change

Change Request

MyPMP
QMS Template

Purpose / summary

Scope / details

Approach / body

Deliverables / outcomes

Notes & sign-off

Part of My QMS — the MyPMP Quality Management System. Template MYPMP-TMPLT-0184 · © MyPMP — mypmp.in. QMS content copyright MyPMP.

Auto-saved in your browser · ★ members can white-label & sync across devices

About the Change Request template

A Change Request is a formal proposal to alter an approved element of a project—scope, schedule, budget, deliverables, or requirements—so the impact can be assessed and authorised before any work happens. It creates an auditable record of who requested what, why, and how the change board decided, protecting the baseline from uncontrolled scope creep.

It's part of My QMS, MyPMP's Quality Management System: fill it in online, personalize it with your name and logo, then export a clean, branded PDF. Your work auto-saves in your browser.

When to use a Change Request

  • A stakeholder asks for a new feature or deliverable not in the agreed scope
  • A defect, risk, or constraint forces a change to schedule, cost, or design
  • A regulatory or contractual requirement shifts mid-project
  • Vendors or clients request variations that affect the approved baseline

What a good Change Request includes

  • Unique CR ID, title, requester, and date raised
  • Description of the change and the reason or business justification
  • Impact analysis across scope, schedule, cost, quality, and risk
  • Priority or urgency and affected work packages or requirements
  • Options considered, including the do-nothing alternative
  • Approval decision, authoriser, and sign-off date

What's inside this template

The interactive form above gives you:

Purpose / summaryScope / detailsApproach / bodyDeliverables / outcomesNotes & sign-off

Tips & common mistakes

  • 💡Quantify the impact—hours, dollars, and dates—rather than describing it vaguely; a CCB cannot decide on 'some delay'
  • 💡Log and number every request even if rejected, so the audit trail stays complete
  • 💡Don't start implementation before formal approval; verbal go-aheads are the most common source of disputes

How it works

  1. 1. Fill it in — type directly into the fields, tables and sections above.
  2. 2. Brand it — add your organization name and logo with the Branding button.
  3. 3. Export — print to PDF, or become a member to white-label and sync across devices.

FAQ

Who approves a Change Request?

Approval typically rests with a Change Control Board (CCB) or the project sponsor, depending on the change's cost and impact threshold defined in your change management plan.

What's the difference between a Change Request and a change log?

A Change Request is the individual proposal for one specific change, while the change log is the register that tracks the status and outcome of all requests across the project.

When should a change go through a formal Change Request?

Any alteration to an approved baseline—scope, cost, schedule, or contractual deliverables—needs a formal request; minor clarifications that don't affect the baseline usually don't.

Make it yours — $9/mo or $99/yr

Membership unlocks white-label export (remove the MyPMP footer), cloud sync across devices, plus all apps & ScheduleX.

See membership
Change Request Template — Free & Interactive | MyPMP · MyPMP