🧠 Can you solve this?Agile Frameworks / MethodologiesMedium⏱ ~90 sec
A team plans a two-week sprint. There are 6 developers, each available 6 productive hours per day for 10 working days. The team reserves 20% of capacity for meetings and unplanned work. How many productive hours are available for committed sprint work?
Choose one answer
More Agile Frameworks / Methodologies challenges
View all →In Scrum, who is accountable for ordering the items in the product backlog to maximize value?A team limits the number of items allowed in each stage of its workflow to expose bottlenecks and improve flow. This practice is characteristic of:In Scrum, the time-box for the Sprint Review of a one-month Sprint is at most:A user story is generally considered complete when it meets the team's agreed:A Scrum team completed the following story points over its last four sprints: 32, 28, 30, and 34. The product backlog contains 186 story points of remaining work. Using the team's average velocity, approximately how many additional sprints are needed to complete the remaining backlog?