🧠 Can you solve this?Agile Frameworks / MethodologiesMedium⏱ ~90 sec

A Scrum team completed the following story points over its last four sprints: 32, 28, 30, and 34. The product backlog contains 186 story points of remaining work. Using the team's average velocity, approximately how many additional sprints are needed to complete the remaining backlog?

Choose one answer