A sprint began with 80 story points committed. At the end of day 4 of a 10-day sprint, 24 points remain incomplete. If work were burning down at the ideal (linear) rate, how many points should remain at the end of day 4?
Choose one answer
More Agile Frameworks / Methodologies challenges
View all βIn Scrum, who is accountable for ordering the items in the product backlog to maximize value?A team limits the number of items allowed in each stage of its workflow to expose bottlenecks and improve flow. This practice is characteristic of:In Scrum, the time-box for the Sprint Review of a one-month Sprint is at most:A user story is generally considered complete when it meets the team's agreed:A Scrum team completed the following story points over its last four sprints: 32, 28, 30, and 34. The product backlog contains 186 story points of remaining work. Using the team's average velocity, approximately how many additional sprints are needed to complete the remaining backlog?