During sprint planning, a team of 7 works a 2-week sprint (10 working days) at 8 hours per day. Applying a focus factor of 60% to account for meetings and interruptions, what is the team's available productive capacity for the sprint?
Choose one answer
More People challenges
View all →Two senior team members disagree openly about the technical approach, and it is slowing the team. What should the project manager do FIRST?A newly formed agile team is unsure of roles and looks to the project manager for direction on nearly every task. According to situational leadership, the PM should adopt a style that is primarily:A key stakeholder frequently changes requirements, frustrating the team. What is the BEST way for the project manager to reduce this going forward?During a retrospective a team member says they feel their contributions are ignored. The servant-leader project manager should:A remote team member consistently misses stand-ups due to time-zone differences and feels disengaged. What should the PM do FIRST?