An agile team's velocity over the last four sprints was 40, 44, 38, and 42 story points. Using the simple average as projected velocity, how many sprints are needed to complete a remaining backlog of 246 story points?
Choose one answer
More People challenges
View all āTwo senior team members disagree openly about the technical approach, and it is slowing the team. What should the project manager do FIRST?A newly formed agile team is unsure of roles and looks to the project manager for direction on nearly every task. According to situational leadership, the PM should adopt a style that is primarily:A key stakeholder frequently changes requirements, frustrating the team. What is the BEST way for the project manager to reduce this going forward?During a retrospective a team member says they feel their contributions are ignored. The servant-leader project manager should:A remote team member consistently misses stand-ups due to time-zone differences and feels disengaged. What should the PM do FIRST?