An activity has an optimistic estimate of 8 days and a pessimistic estimate of 26 days. Using the PERT (beta) distribution, what is the standard deviation of this activity's duration estimate?
Choose one answer
More Process challenges
View all βA project has EV = 800, PV = 1000, and AC = 1000. Which statement is correct?With CPI = 0.8 and a BAC of 100,000, what is the estimate at completion (EAC) assuming current cost performance continues?A risk that would have a positive impact on the project is best handled by strategies such as:In a hybrid project, the team delivers in iterations but must meet a fixed regulatory go-live date. The BEST way to keep scope realistic is to:A sponsor asks for a new high-value feature mid-project. What should the project manager do FIRST?