🧠 Can you solve this?ProcessMedium⏱ ~90 sec

A project's control account estimates total $450,000. In addition, the project manager identifies $50,000 in contingency reserves for known risks and management approves $40,000 in management reserves for unknown risks. What is the project's cost baseline?

Choose one answer