A project manager faces a risk with three possible outcomes: a 20% chance of a $50,000 loss, a 40% chance of a $30,000 loss, and a 10% chance of an $80,000 loss (the remaining probability results in no impact). What total contingency reserve should be set based on expected monetary value (EMV)?