A project has a budget at completion (BAC) of $100,000. At the status date, earned value (EV) = $20,000, actual cost (AC) = $40,000, and planned value (PV) = $25,000. Management believes the current cost AND schedule inefficiencies will both continue for the remaining work. What is the estimate at completion (EAC)?