A network diagram has activity A (5 days) starting the project. Two parallel activities follow: B (6 days) and C (4 days), both starting when A finishes. Both B and C must complete before activity D can begin. What is the free float of activity C?
Choose one answer
More Process challenges
View all βA project has EV = 800, PV = 1000, and AC = 1000. Which statement is correct?With CPI = 0.8 and a BAC of 100,000, what is the estimate at completion (EAC) assuming current cost performance continues?A risk that would have a positive impact on the project is best handled by strategies such as:In a hybrid project, the team delivers in iterations but must meet a fixed regulatory go-live date. The BEST way to keep scope realistic is to:A sponsor asks for a new high-value feature mid-project. What should the project manager do FIRST?