🧠 Can you solve this?Agile Principles & MindsetHard⏱ ~90 sec

A team of 5 developers works a 2-week iteration of 10 working days at 6 productive hours each per day. Based on past data, the team's focus factor (productive capacity available for backlog work) is 70%. What is the team's available capacity in hours for the iteration?

Choose one answer