A team of 5 developers works a 2-week iteration of 10 working days at 6 productive hours each per day. Based on past data, the team's focus factor (productive capacity available for backlog work) is 70%. What is the team's available capacity in hours for the iteration?
Choose one answer
More Agile Principles & Mindset challenges
View all →Which statement best reflects the Agile Manifesto's values?A stakeholder demands a fixed, detailed scope for a 12-month agile program up front. The BEST response is to:Which of the following best reflects an empirical process control used in agile?An agile principle states that working software should be delivered frequently. According to the Agile Manifesto, what should teams primarily use to measure progress?A team is working long hours of overtime to hit an aggressive deadline, and morale and quality are declining. Which agile principle should guide the leader's response?