🧠 Can you solve this?Project Management Fundamentals & Core ConceptsMediumā± ~90 sec

An activity has an optimistic estimate of 4 days, a most likely estimate of 10 days, and a pessimistic estimate of 22 days. Using the PERT (beta) distribution, what is the standard deviation of the activity duration?

Choose one answer