A project manager is measuring schedule performance. The budget at completion (BAC) is $200,000. At the reporting date, planned value (PV) is $90,000 and earned value (EV) is $75,000. What is the schedule variance (SV)?
Choose one answer
More Predictive, Plan-Based Methodologies challenges
View all →In a predictive life cycle, the decomposition of project deliverables into smaller, more manageable components produces the:An activity has an optimistic estimate of 6 days, a most likely of 12 days, and a pessimistic of 30 days. Using the PERT (beta) three-point estimate, the expected duration is:On a network diagram, the total float of an activity on the critical path is normally:Activity B (3 days) can start only after Activity A (5 days) finishes. This dependency is best described as:A cost baseline is best described as: