A project has a budget at completion (BAC) of $200,000. At the status date, the earned value (EV) is $80,000, the actual cost (AC) is $100,000, and the planned value (PV) is $90,000. What is the cost variance (CV)?
Choose one answer
More Project Management Fundamentals & Core Concepts challenges
View all →A project is best described as which of the following?During which activity does the project manager formally authorize the project and gain the authority to apply resources?A stakeholder register is primarily used to:Which of the following is an example of a project constraint?A change request has been submitted. In a predictive project, who typically approves or rejects it?